Back to Home Page

 
 

Contracts Awarded:

 
 Click on the Tender No. or Contract No. to See Details
       

Tender No.

Contract No.

Contract Date

Contractor

Name of the Work

Completion Date

CE/CON/H-L/TL/ 2017/06

W/362/CON/H-L/ TL/2017/06

08/09/2017

DCC-Babul Nath (JV)

Linking of BG track with 60kg single/long welded panels with 1660 nos. PSC sleeper per km in main line and 52 kg single/three rails welded panels with 1540 nos. PSC sleeper per km in loop lines including linking of 1 in 12, 1 in 8.5 and derailing switches on PSC sleepers (Fan shaped layout), laying of SEJs etc. dismantling of BG track, point & Xings from km 145.500 including HJI yard to Km 190.50 in between PKB and LMG in connection with HJI-LMG patch doubling works.(Two Packet System)

04/08/2019

CE/CON/N-K/EMB/ 2016/ 22(RT-1)

W/362/CON/N-K/EMB/ 2016/22(RT-1)

08/03/2017

NCDC- GPT (JV)

Construction of BG standard formation, minor bridge, retaining wall, side drain and catch water drain including all other ancillary works from km 115.00 (including Boko station yard) to km 154.00 (including Mirza station yard) in connection with NBQ-KYQ BG Doubling project. (Two Packet system).

08/02/2019

CE/CON/N-K/EMB/ 2016/21(RT-1)

W/362/CON/N-K/EMB/ 2016/21(RT-1)

08/03/2017

ABCI Infrastructures Pvt. Ltd.

Construction of BG standard formation, Minor Bridges, Retaining wall, Side drain, Catch water Drain including all ancillary works from Km: 79.00 (excluding Dudhnoi Station Yard) to Km: 115.00 (including Singara Station yard) in connection with doubling of existing BG line from NBQ to KYQ via GLPT. (Two Packet System).

08/02/2019

CE/CON/B-S/Tunneling Work/2016/27

W/362/CON/B-S/ Tunneling Work/ 2016/27

25/07/2017

Nayak Infrastructure Pvt. Ltd.

Construction of single line BG tunnel no.11-A (600 Rm) from Km 22.850 to Km 23.450 including all other ancillary works between stations Hortoki & Kawnpui in connection with the construction of new BG railway line from Bhairabi to Sairang (Mizoram) (Two Packet System).

24/01/2019

CE/CON/K-A/FOB/ 2017/02

CE/CON/K-A/FOB/ 2017/02

20/07/2017

M/s. Tribeni Constructions Ltd.

Construction of Pedestrain FOB of 6m width and 159m length for connecting road passing through Jirania yard with other miscellaneous work in between Kumarghat-Agartala section in connection with Kumarghat-Agartala new BG Line (Ph-II) project.

19/07/2018

CE/CON/L-S/ROB/ 2017/02(RT-1)

W/362/CON/L-S/ROB/ 2017/02(RT-1)

07/12/2017

M/s. R.L. Construction

Construction of ROB (Road Over Bridge) 1 X 24.00 m clear span composite girder welded type on cast in situ bored RCC piles of 1200 mm dia along with ancillary works at Km 46/4-5 between sections DMR-PASG in connection with LMG-SCL GC work of N.F. Railway.

03/11/2018

CE/CON/AGTL-Sabroom/Misc. Work/2016/30

W/362/CON/AGTL-Sabroom/Misc. Work/2016/30

07/12/2017

RL-JMO (JV)

At Bishalgarh - Balance work for Construction of quarter, Colony Area Development, Pipeline installation of overhead tank etc. extension of High Level Platform No. 1 along with extension of Br. No.45 both ends, Construction of Rail Level Platform No.2, extension of PP Shed, construction of Yard drains, Children Park and other ancillary works in connection with Agartala-Sabroom New Line Project (Two Packet system).

03/11/2018

CE/CON/T-B/Bldg. Work/2016/35

W/362/CON/T-B/Bldg. Work/2016/35 dt.

07/11/2017

M/s. Tama & Taba Sera (JV)

At Byrnihat (Meghalaya) construction of staff quarter (T-II, III, IV), OH Tank, FOB, Approach Road, PF, Washable apron, Goods office & shed, P.way Godown, Commercial office & labour room and other ancillary works in connection with Tetelia-Byrnihat New line Railway Project (Two Packet System)

01/10/2019

CE/CON/D-H/EMB/ 2017/02

W/362/CON/D-H/EMB/ 2017/02

07/06/2017

Tribeni Constructions Ltd.

Construction of BG standard formation, minor bridges including retaining wall, side drains, catch water drains, formation treatment of bad banks and all other connected ancillary works in between Km 98.00 (Excluding Hojai Station yard) to Km 145.00 in connection with Digaru-Hojai Double Line Project of N.F. Railway. (Two Packet System)

01/05/2019

CE/CON/D-H/EMB/ 2017/01

W/362/CON/D-H/ EMB/2017/01

07/06/2017

N.C. Das - Allied Infra (JV)

Construction of BG standard formation, minor bridges including retaining wall, side drains, catch water drains, ground improvement works and all other connected ancillary works in between km 44.13 (including Digaru Station yard) to km 98.00 in connection with Digaru-Hojai Double Line Project of N. F. Railway. (Two Packet System)

01/05/2019

CE/CON/T-B/Tunneling Work/2016/46

W/362/CON/T-B/ Tunneling Work/2016/46

07/06/2017

ABCI Infrastructures Pvt. Ltd.

Construction of BG tunnel at Km 21/130 to 21/430 (length = 300.00m) and 03 nos. of Cut & cover at Km 16/900 to 17/000, 17/175 to 17/275 & 19/700 to 19/800 respectively in between station Kamalajari - Byrnihat including earthwork in formation to make profile as per BG standard and other miscellaneous works at approaches in connection with Tetelia - Byrnihat New Line Project. (Two Packet System)

01/05/2019

CE/CON/NCB-GUZ/Misc. Work/2016/25

W/362/CON/NCB-GUZ/Misc. Work/2016/25

07/06/2017

Shubhashis Chakraborty

Supplying, fitting and fixing of level crossing, lifting barrier, fencing, all types of sign boards, construction of approach road, gate quarters, fixing of kilometer post and hectometer post, painting of bridge, construction of bridge inspection steps, providing fouling mark and other ancillary works in between km 126.19 to km 96.87 in connection with NCB-GUZ Doubling Project.

04/05/2018

CE/CON/J-I/MB/2016/ 23(RT-1)

W/362/CON/J-I/MB/ 2016/ 23(RT-1)

07/03/2017

Tribeni Constructions Ltd.

Construction of sub-structure of bridge No.137-B having span 3x30.00m, at ch.73.910 km (Curve) including other ancillary works in connection with construction of new BG Railway line from Jiribam to Tupul (Manipur) Project. (Two Packet System)

11/02/2018

CE/CON/J-I/MB/2016/27

W/362/CON/J-I/MB/ 2016/27

30/06/2017

ABCI Infrastructure Pvt. Ltd.

Construction of sub-structure of bridge No.176 having span 3x30.50m, at km 97.906 km (2” Curve) including other ancillary works in connection with construction of new BG Railway line from Jiribam to Tupul (Manipur) project.

29/10/2018

CE/CON/B-S/Tunnel-1A-3/ 2016/24

W/362/CON/B-S/ Tunnel-1A-3/ 2016/24

23/06/2017

Nayak Infrastructure Pvt. Ltd.

Construction of Single line BG tunnel No.1-A (160 Rm) from km 4.630 to km 4.520 and tunnel No.3 (220 Rm) from km 13.237 to km 13.457 by ADECO-RS Method including all other ancillary works between stations Bhairabi & Kownpui in connection with the construction of new BG Railway line from Bhairabi to Sairang (Mizoram).

22/12/2018

CE/CON/B-S/MB/2016/15

W/362/CON/B-S/MB/ 2016/15

23/06/2017

VKGA-Brahmaputra-Tribeni (JV)

Construction of foundation and sub structure over pile foundation for Tall Bridge no.161-162-163 (span 1 x 47.74 + 7 x 78.80 + 1 x 47.7m steel girder) at Km 42.360 including all other ancillary works and protection works in between stations Bhairabi and Sairang in connection with the construction of new BG Railway line from Bhairabi to Sairang (Mizoram).

22/02/2019

CE/CON/J-I/MB/2016/26

W/362/CON/J-I/MB/ 2016/26

19/06/2017

M/s. Tribeni Constructions Ltd.

Construction of sub-structure of bridge No.169-C (span 3x45.00m, at km 94.797 & Br. 172 (span 1x45.00m) Km 96.492 including other ancillary works in connection with construction of new BG Railway line from Jiribam to Tupul (Manipur) project.

18/12/2018

CE/CON/A-S//TN/2016/ 28(RT-1)

W/362/CON/A-S//TN/ 2016/ 28(RT-1)

16/06/2017

M.K. Engineering

Construction of Tunnel by Cut & Cover method from Ch. 53.615 Km to 53.775 Km between Garjee Santirbazar section in connection with construction of Agartala-Sabroom New BG Line Project.

15/12/2017

CE/CON/L-S/GCA/ 2017/01

W/362/CON/L-S/GCA/ 2017/01

13/06/2017

Shri Ashok Deb

Construction of goods circulating area and approach road at BXG and New KXJ Yard in connection with LMG-SCL project.

12/12/2017

CE/CON/D-H/Bldg. Work/2016/36

W/362/CON/D-H/Bldg. Work/2016/36

06/12/2017

M/s. A.T. Trade Agency

At Sonuabari, Dharamtul & Thekaraguri station construction of 33 units type-II and 3 unit type-III staff Quarters with other ancillary works in connection with Digaru-Hojai Double line project of N.F. Railway.

06/11/2018

CE/CON/MLA/Qtr/DGU-HJI Doubling/2016/37

W/362/CON/MLA/Qtr/ DGU-HJI Doubling/ 2016/37

06/12/2017

M/s. A.T. Trade Agency

Construction of foundation and sub structure over pile foundation for Tall Bridge no.167 (span 1x28.50m + 6x78.80 steel girder) at Ch: 44996.65 and bridge no:169 (5x30.5 composite girder) at Ch:45552.49m including all other ancillary works and protection works in between stations Bhairabi and Sairang in connection with the construction of new BG Railway line from Bhairabi to Sairang (Mizoram)

06/11/2020

CE/CON/B-S/MB/2016/13

W/362/CON/B-S/MB/ 2016/13

06/06/2017

M/s. MK - Pusphas (JV)

Construction of foundation and sub structure over pile foundation for Tall Bridge no.167 (span 1x28.50m + 6x78.80 steel girder) at Ch: 44996.65 and bridge no:169 (5x30.5 composite girder) at Ch:45552.49m including all other ancillary works and protection works in between stations Bairabi and Sairang in connection with the construction of new BG Railway line from Bhairabi to Sairang (Mizoram).

06/05/2018

CE/CON/B-S/MB/2016/12

W/362/CON/B-S/MB/ 2016/12

06/06/2017

VKGA-Brahmaputra-Tribeni (JV)

Construction of foundation and sub structure over pile foundation for Tall Bridge no.115 (6x103.50m + 1 x 47.24m steel girder) at Ch: 34765m including all other ancillary works and protection works in between stations Bhairabi and Sairang in connection with the construction of new BG Railway line from Bairabi to Sairang (Mizoram)

02/05/2019

CE/CON/H-I/MB/2016/47

W/362/CON/H-I/MB/ 2016/47

06/06/2017

M/s. Tama Fabrication Work

Supply, fabrication and erection of road bridge (of span 4x45.0m open web girders) over river Pachin at Naharlagun as per plan.

12/05/2018

CE/CON/J-I/Road Work/ 2016/32

W/362/CON/J-I/Road Work/2016/32

06/06/2017

Creative Consultant & Builders

Earthwork and minor Bridges for new road construction, repair to existing road for providing accessibility to tunnels portals/Adits for providing infrastructure in connection with relief and rescue/security mobility in the stretches covering tunnel No.1 to Bridge No.44 between Dholakhal & Kaimai Road in connection with construction of new BG line between Jiribam to Tupul.

02/05/2018

CE/CON/N-K/Misc. Work/ 2016/44

W/362/CON/N-K/Misc. Work/ 2016/44

06/06/2017

Nandigiri Bhuyan

Construction of approach/diversion road, drain & safety related works, transportation & handling of railway materials and other ancillary works from Km 88/0 to 132/0 between Amjonga (Excluding) and Chayagaon station (Excluding) in connection with NBQ-GLPT-KYQ Doubling project.

12/05/2018

CE/CON/N-K/MB/2016/09

W/362//CON/N-K/MB/2016/09

19/12/2016

Nayak Infrastructure Pvt. Ltd.

Construction of foundation and sub-structure of major bridges between Km: 122.00 to Km: 176.00 including earthwork in formation to make profile as per BG standard and other miscellaneous works at approaches in connection with NBQ - KYQ Doubling works in N. F. Railway.

18/12/2018

CE/CON/N-K/MB/2016/07

W/362/CON/N-K/MB/2016/07

14/12/2016

Nayak Infrastructure Pvt. Ltd.

Construction of foundation and sub-structure of major bridges between Km: 0.00 to Km: 60.00 including earthwork in formation to make profile as per BG standard and other miscellaneous works at approaches in connection with NBQ - KYQ Doubling works in N. F. Railway

13/12/2018

CE/CON/N-K/MB/2016/08

W/362/CON/N-K/MB/2016/08

12/09/2016

M/s Shivam - Pusphas (JV)

Construction of foundation and sub-structure of major bridges between Km: 60.00 to Km: 122.00 including earthwork in formation to make profile as per BG standard and other miscellaneous works at approaches in connection with NBQ - KYQ Doubling works in N. F. Railway

12/08/2018

CE/Con/DMV - KOHIMA/Bridge Design/2016/10

W/362/Con/DMV - KOHIMA/Bridge Design/2016/10

12/09/2016

Stup Consultant Pvt. Ltd.

Design of various bridges and related geotechnical investigations between proposed stations Sukhovi & Zubza in connection with Dimapur - Kohima New BG line project.

12/08/2018

CE/CON/GUZ - NCB/Ballast/2016/27

W/362/CON/GUZ - NCB/Ballast/2016/27

12/05/2016

Durga Krishna Store Pvt. Ltd.

Manufacturing, supplying and stacking into cess 50mm size hard machine crushed Pakur variety stone ballast at nominated places in between Km. 112.50 to Km.127.00 in of SJRR - NCB section in connection with construction of NCB- GUZ Doubling project.

06/04/2018

CE/Con/ HJI - LMG/ Ballast/ 2016/ 08

W/362/Con/ HJI - LMG/ Ballast/ 2016/ 08

30/11/2016

Parikshit Chandra Das

Manufacturing, supplying and stacking 65000 Cum machine crushed stone ballastbetween Km 145.500 to Km 190.00 at depot / cess in connection with LMG - HJI Patch doubling project.

29/05/2018

CE/CON/B-S/MB/2016/19

W/362/CON/B-S/MB/2016/19

21/11/2016

M/s R. L. construction

Construction of foundation and sub structure over pile foundation for major bridge no 181 (2x61.0m, steel girder Ch. 46898.6m), 183 (4x 30.5mm, steel girder Ch. 47287.7m), 186-187 (1x 45.7m, steel girder Ch. 47771.88m), & 194 - 195 (2x30.5mComposite girder Ch. 48467.00m ) including all other ancillary works and protection works required for successful completion of the job in between stations Bairabi and Sairang in connection with the construction of new BG railway line from Bairabi to Sairang (Mizoram).

20/11/2018

CE/CON/DMV-Kohima/Bldg.Work/2016/07

W/362/CON/DMV-Kohima/Bldg.Work/2016/07

11/04/2016

M/s E. S. - M. P. (JV)

Construction of Camp office cum temporary accommodation at Dimapur, Type-IV (6 units), Type-III (18 units) & Type-II (36 units) quarters in single/multistoried (up to Triple storied) buildings at Dimapur, Dhansiripar & Shokhuvi stations & related miscellaneous work in connection with the Dimapur (Dhansiri) – Kohima (Zubza) New Line Project

05/03/2018

CE/CON/GUZ - NCB/Ballast/2016/26

W/362/GUZ - NCB/Ballast/2016/26

11/02/2016

Prabhu Projects Pvt. Ltd.

Manufacturing, supplying and stacking into cess 50mm size hard machine crushed Pakur variety stone ballast at nominated places in between Km. 96.00 to Km.112.50 in of GUZ- SJRR section in connection with construction of NCB- GUZ Doubling project.

05/01/2018

CE/Con/B-S/ Cut and Cover/ 2016/08

W/362/Con/B-S/ Cut and Cover/ 2016/08

31/10/2016

Pyrkhat Hinge

Construction of cut & cover, retaining wall and other ancillary works between Km 0.780 to 0.860, Km 0.880 to 0.940 and Km 0.980 to 1.040 (approx length 200 RM) in between station Bairabi and Proposed station Hortoki in connection with the construction of new BG railway line from Bairabi to Sairang (Mizoram)

30/10/2017

CE/Con/ NCB-SMTA/Cess Ballast/2016/34

W/362/Con/ NCB-SMTA/Cess Ballast/2016/34

26/10/2016

Prabhu Projects Pvt. Ltd.

Manufacturing, supplying and stacking into cess 50mm size hard machine crushed stone ballast of approved quality at nominated places in between Km. 144.50 to Km.134.00 in of NBS - NOQ section connection in connection with construction of NCB- SMTA Doubling project.

25/10/2017

CE/CON/ B-S/ ROB - RUB/ 2016/ 06

W/362/CON/ B-S/ ROB - RUB/ 2016/ 06

25/10/2016

Durga Krishna Stores Pvt. Ltd.

Construction of 4 nos of ROB for bridges 187 (Ch. 47482.378m), 190 (Ch. 47960.00m), 197 (Ch. 49036.121m) & 195-A (Ch. 48602.000m) and 1 RUB for bridge no 144 (Ch. 37898.004m) along-with pucca approach road and other ancillary works in between station Bairabi and Sairang in connection with construction of New BG line from Bairabi to Sairang.

24/10/2017

CE/CON/DMV - KOHIMA/Tunnel/ 2016/06

W/362/CON/DMV - KOHIMA/Tunnel/ 2016/06

10/05/2016

ABCI Infrastructure Pvt. Ltd.

Construction of single line BG tunnel (3 nos. approximate total length 3960RM) including cut and cover portion, earthwork in bank & cutting to make formation, construction of minor bridges, toe walls, retaining walls, other protection and ancillary works in between Ch. 20500 to Ch. 27200 in between station Sukhovi & Molvom in connection with DMV - KOHIMA New Line Project.

04/04/2019

CE/CON/NCB - SMTA/ Protection Work/ 2016/07

W/362/CON/NCB - SMTA/ Protection Work/ 2016/07

19/10/2016

Durga Krishna Stores Pvt. Ltd.

Protection work of major and minor bridges, balance earthwork in formation, provision of RCC/ CRM retaining wall, embankment toe protection work, supply and spreading of blanketing material on the top of the formation and other ancillary works in between stations NBS & NOQ in connection with Doubling of BG line project between NCB - SMTA.

18/10/2017

CE/CON/J - I/Parallel T-12/2016/11

W/362/CON/J - I/Parallel T-12/2016/11

10/12/2016

HCC-VCCL (JV)

Construction of parallel safety tunnel of T-12 at Km 105/650 to Km 115/176 in between Tupul – Imphal in connection with construction of New Railway Line Project Jiribum– Imphal of N. F. Railway.

10/11/2020

CE/CON/B-S/MB/2016/18

W/362/CON/B-S/MB/2016/18

17/10/2016

M/s MK - Puspas (JV)

Construction of foundation and sub structure over pile foundation for major bridge no 93 (5x30.50m steel girder) at ch.31390.76m, Bridge No 101 (1x18.3 + 5x30.5 + 1x18.3 composite girder) at Ch 32828.00 and Bridge No 117+118 (10x30.5 composite girder) at Ch 35388.00 including all other ancillary works and protection works required for successful completion of the job in between stations Bairabi and Sairang in connection with the construction of new BG railway line from Bairabi to Sairang (Mizoram).

16/04/2018

CE/CON D-L MB 2015 10

W/362/CON D-L MB 2015 10

14/10/2016

Macrocosm - Samim (JV)

Construction of foundation and sub-structure of major bridges between Km: 44.00 to Km: 77.00 including earthwork in formation to make profile as per BG standard and other miscellaneous works at approaches in connection with Digaru to Hojai Doubling works in N. F. Railway.

13/04/2018

CE/Con/H - L/ Carriage/ 2016/06

W/362Con/H - L/ Carriage/ 2016/06

10/12/2016

Prem Kumar & Co.

Loading / Unloading of rails 60 Kg (New) / 52 Kg (S/H) from railway wagon including carriage of rail, switches, crossing bodies etc. from Lumding and PSC line sleepers / Special sleepers from Jagir Road, Mirza and New jalpaiguri sleeper plants to various stations / locations / Block section in between Hojai to Lumding in connection with Hojai Lumding Patch Doubling Project.

10/11/2017

CE/CON/AGTL-Sabroom/BG Track Linking/2016/11

W/362/CON/AGTL-Sabroom/BG Track Linking./2016/11

28/09/2016

Arihant Construction

Linking of New BG Track, Spreading of ballast on newly constructed BG formation along with all other ancillary works between KM 90.000 to 114.134 including Assembling & Laying of Points & Crossing etc. including Manubazar & Sabroom yards in connection with Agartala – Sabroom, New BG Line Project.

27/09/2017

CE/CON/B-S/MB-38,40,41 &42/2016/05

W/362/CON B-S MB 38 40 41 And 42 2016 05

28/09/2016

Draipl-ABCI (JV)

Construction of foundation and sub-structure on pile foundation for major bridges no 38 at ch. 14188.00m; bridge no 40 at ch. 14850.00m, bridge no 41 at ch. 15006.00m and bridge no 42 at ch. 15148.00m, protection works and other ancillary works in between stations Bhairabi and Sairang in connection with construction of new BG line from Bhairabi to Sairang (Mizoram) N. F. Railway.

27/12/2017

CE/CON/Bogibeel Bridge/Protection work/2016/03

W/362/CON/Bogibeel Bridge /Protection Work/2016/03

16/09/2016

Kulen Hazarika

Special works to fill up the scour pocket in the river bed along the lauching apron of the south guide bund from chainage 400.00m to 1400.00m (BCL) with geo-bags, gabion boxes filled with geo bags and supply weaving / making of GI wire sausage crate wire netting etc. in connection with Bobibeel Bridge Project.

15/03/2018

CE/Con/DMV - KOHIMA/ DDC- Instrumentation/ 2016/01

W/362/Con/DMV - KOHIMA/ DDC- Instrumentation/ 2016

15/09/2016

Bearer Infra Consultancy Pvt. Ltd.

Detailed design and construction supervision including instrumentation of single line BG tunnels (3nos Approximate length 3960m) including cut and cover between proposed stations Sukhovi and Molvom in connection with construction of new line between DMV and Kohima.

14/09/2019

CE/CON/J-I /Tunnel-4A/2016/02

W/362/CON/J-I /Tunnel-4A/2016/02

15/09/2016

M/s.Sushee Infra & Mining Ltd.

Construction of single line BG Tunnel No. T-4A (approx length 460.00 RM) at Km 102/550 to 103/010 in between Tupul – Imphal in connection with construction of New Railway Line Project Jiribum – Imphal of N.F Railway.

14/03/2018

CE/CON/B-S/MB-56/2016/07

W/362/CON/B-S/MB-56/2016/07

09/12/2016

Nayak-ST Enterprise (JV)

Construction of foundation and sub structure over pile foundation fpr major bridge no 56 in between Ch. 18.715 Km and 18.775 Km and other ancillary works and protection works in between stations Bairabi and Sairang in connection with the construction of new BG railway line from Bairabi to Sairang (Mizoram)

06/11/2017

CE/CON L -H EMB 2016 02

W/362/CONL - H EMB 2016 02

08/08/2016

Asean Agencies - MKL Associates (JV)

Execution of Civil Engineering works for construction of BG standard formation, retaining wall, side drains, catch water drains, minor bridges and other ancillary works in between Km 169.00 to km 190.00 in connection with HJI – LMG Doubling works in N. F. Railway.

02/07/2018

CE/CON/J-I /Building Work/2016/04

W/362/CON/J-I /Building Work/2016/04

27/08/2016

M/s ES - MP (JV)

Construction of 112 units staff quarters (Type-II-92 units, Type-III-16 units, Type-IV-4 units), Office Complex, Sub-Ordinate Rest House, Health Unit, Security Barrack, Crew Rest Room, Sub-Ordinate Offices, Godown, Boundary wall, Colony and Office approach road, pipe-line, drainage system and other ancillary works in connection of new BG Railway line from Tupul-Imphal.

26/02/2018

CE/CON DMV-KOHIMA Bldg. Work 2015 08

W/362/CON DMV-KOHIMA Bldg. Work 2015 08

08/11/2016

M/s Kuhoi Zhimo

Construction of station buiding, passenger platform, Staff quarters, Overhead tank etc. at Dhansiri Station and construction of temporary accomodation for security personnel including other ancillary works in connection with Dimapur - Kohima new line project.

08/10/2017

CE/CON B-S MB 21, 22 And 23 2016 03

W/362/CON B S MB 21 22 And 23 2016 03

08/12/2016

Bharatia Infra Projects Ltd.

Construction of foundation and sub-structure on pile foundation for major bridges no 21 at ch. 7736.00m, bridges no 22 at ch. 8062.00m & bridges no 23 at ch. 8677.00m, protection works and other ancillary works in between stations Bhairabi and Hartoki in connection with construction of new BG line from Bhairabi to Sairang (Mizoram) N. F. Railway.

02/11/2018

CE/CON B-S MB 24 & 27 2016 04

W/362/CON B-S MB 24 and 27 2016 04

23/08/2016

N. C. Das & Co.

Construction of foundation and sub structure on pile foundation for major bridge No.24 at ch.9010.00m, & bridge No.27at ch.10095.00m protection works and other ancillary works in between stations Bhairabi and Hartoki in connection with construction of new BG line from Bhairabi to Sairang (Mizoram) N.F.Railway.

22/11/2017

CE/CON/Bogibeel Bridge /Protection Work/2016/02

W/362/CON/Bogibeel Bridge /Protection Work/2016/02

17/08/2016

Bharatia Infra Projects Ltd.

Repair and protection to embankment slope and protection work of major and minor bridge between km 16.00 to Br No: 43 and Y connection (Moran to bogibeel bridge), track linking and ancillary works between Km 19.00 to Bogibeel Main bridge approach (23.341 Km), repairs and renovation of RBG room at 19.00 Km, approach road etc. in connection with construction of Bogibeel Bridge Project.

16/02/2018

CE/CON B-S MB 12, 15, 19 And 20 2016 01

W/362/CON/ B S MB 12 15 19 And 20 2016 01

08/12/2016

Nayak Infrastructure Pvt. Ltd.

Construction of foundation and sub-structure on pile foundation for major bridges no 12 at ch. 1941.00m; bridge no 15 at ch. 4080.00m, bridge no 19 at ch. 6300.00m and bridge no 20 at ch. 7043.00m, protection works and other ancillary works in between stations Bhairabi and Hartoki in connection with construction of new BG line from Bhairabi to Sairang (Mizoram) N. F. Railway.

11/11/2017

CE/CON B-S MB 17 2016 02

W/362/CON B-S MB 17 2016 02

08/12/2016

ECI - Nayak (JV)

Construction of foundation and sub-structure on pile foundation for major bridges no 17 at ch. 5020.00m, protection works and other ancillary works in between stations Bhairabi and Hartoki in connection with construction of new BG line from Bhairabi to Sairang (Mizoram) N. F. Railway.

02/11/2018

CE/CON/MLG/G Plus 5/Admn.Bldg/2014/15

W/362/CON/MLG/G Plus 5/Admn Bldg/2014/15

08/10/2016

M/s SHASS Engineers

Construction of (G+5) Administratie Building having Car parking with the provision of landscaped court and other ancillary works in the premises of GM/Const.) Office.. Tender value Rs. 17, 07, 34, 225.00 Earnest money: Rs.10, 03, 680.00, Completion period:(20) months, Cost of Tender documents: Rs. 10,000/- to be paid through payment gateway available at e-tendering portal. Cost of the tender document is non-refundable.

04/09/2018

CE/CON L -H EMB 2016 01

W/362/CONL - H EMB 2016 01

08/08/2016

DCC - Babul Nath (JV)

Execution of Civil Engineering works for construction of BG standard formation, retaining wall, side drains, catch water drains, minor bridges and other ancillary works in between Km 145.50 to km 169.00 in connection with HJI – LMG Doubling works in N. F. Railway.

02/07/2018

CE/CON/Bogibeel Bridge/Protection work/2016/01

W/362/CON/Bogibeel Bridge/Protection work/2016/01

08/04/2016

B. L. Agarwala

Quarrying and supplying of 75000 Cum (approx.) man size blasted boulder for flood reserve stock weighing 40 Kg. to 70 Kg. and stacking at Bogibeel Bridge site (inside dyke) on South Bank of river Brahmaputra in connection with construction of Bogibeel Bridge Project at Bogibeel near Dibrugarh. (Two Packet System).

02/03/2018

CE/CON D-L MB 2015 11

W/362/CON/ D-L MB 2015/11

08/04/2016

ABCI Infrastructure Pvt. Ltd.

Construction of foundation and sub-structure of major bridges between Km: 77.00 to Km: 138.00 including earthwork in formation to make profile as per BG standard and other miscellaneous works at approaches in connection with Digaru to Hojai Doubling works in N. F. Railway.

02/03/2018

CE/CON/Bogibeel/Protection work/2015/28

W/362/CON/Bogibeel/Protection work/2015/28

07/12/2016

Shivam Transcon Pvt. Ltd.

Approach protection work of all major and minor bridge between Chainage 28282.50m to 46400m at North Bank side in connection with Bogibeel Bridge Project.

01/11/2017

CE/CON/ NMX-JPZ/ EMB/ 2016/ 04

W/362/CON NMX JPZ EMB 2016 04

07/12/2016

Kulen Hazarika

Balance Earthwork in filling/cutting for making of Railway embankment and construction of Minor Bridges, RUB and other ancillary works including Protection works from 240/000 KM to Ch.245/680 KM in between Bechimari – Abhayapuri Section of NMX-JPZ New BG Line Project.

07/11/2017

CE/CON/LMG-SCL/ Instrumentation/S/2016/01

W/362/CON/LMG-SCL/ Instrumentation /S/ 2016/01

05/09/2016

Geo Consult-RITES (JV)

Instrumentation, monitoring and design of remedial works as per requirement for vulnerable locations for two monsoon seasons in Lumding -Silchar BG Rail line.

05/08/2018

CE/CON/RNY MZS P Way Works 2016 02

W/362/CON/RNY MZS P Way Works 2016 02

05/11/2016

Bhattacharjee & CO.

P.way maintenance work for assisting track machines and other connected works in between Km. 297/0 (NLP excluding) to 450/0 (MZS including) in connection with RNY - MZS GC Project.

05/10/2017

CE/CON/ NMX-JPZ/ Protection Work/ 2016/ 05

W/362/CON/ NMX-JPZ/ Protection Work/ 2016/ 05

05/11/2016

Ashim Kumar Ghosh

Construction of concrete toe wall, random rubble masonry wall, Cross drain, proving sausage crate, etc.. For protection of railway embankment and other ancillary works between section Km 210.000 to Km 215.000 in connection with construction of new BG line

03/10/2017

CE/CON/DMV-Kohima/EMB/2015/05

W/362/CON/DMV - KOHIMA/EMB/2015/05

18/04/2016

M/s. Nayak Infrastructure Pvt. Ltd.

Earthwork in bank and in cutting for regrading of existing formation and construction of New bank, Extension of existing bridges and construction of New minor bridges, Retaining walls, Toe walls, other protection and ancillary works for regrading of Dhansiri – Rangapahar Section, Dhansiri yard and New line upto river Dhansiri in connection with Dimapur (Dhansiri) – Kohima (Zubza) New BG Line Project.

17/10/2017

CE/CON/B-S/EMB/2015/24

W/362/CON/B-S/EMB/2015/24

03/11/2016

B.Patel Infrastructure Pvt.Ltd.

Earthwork in cutting to form formation, earthwork in filling to form embankment and construction of minor bridges, retaining wall, pucca approach road to alignment and other ancillary work at Sairang station between chainage km 49.2 to km 51.30 in connection with the construction of new BG Railway line from Bairabi to Sairang (Mizoram).

03/10/2017

CE/CON/DMV-Kohima/MB/2015/11

W/362/CON DMV-KOHIMA MB 2015 11

18/03/2016

Bhartia Infra Projects Ltd.

Construction of substructure and super structure (in pile foundation) and super structure (in composite girder) of bridges over rivers Dhansiri, langlong, Disangphu Jan and bridge No.41 near Sukhovi, earthwork in approach banks/ guide bunds, protection and other related works between stations Dhansiri and Sukhovi in connection with Dimapur-Kohima new line project.

17/03/2018

CE/CON/LMG-SCL/Diesel Shed/2015/18

W/362/CON/LMG-SCL/Diesel Shed/2015/18

02/11/2016

Jyoti-KKBE (JV)

At Lumding – Conversion of existing MG Diesel Locomotive Shed into BG Diesel Locomotive Shed for homing/maintaining 100 HHP Locos in connection with LMG-SCL Gauge Conversion Project.

02/10/2017

CE/CON/NMX-JPZ/MB/ 2015/07

W/362/CON/NMX JPZ/MB/2015/07

10/12/2015

N.C.Das & Co.

Balance work of construction of Pile foundation, Sub-structure and Super-structure of PSC Slab Bridge No.190 (6 x 12.20m), 194 (2 x 12.20m), 199 (2 x 12.20m), 204 (5 x 12.20m), 205 (3 x 12.20m), 213 (3 x 12.20m) and Bridge No. 220 (5 x 12.20m) at Ch. 166.940 KM, 170.750 KM, 175.254 KM, 177.600 KM, 178/100 KM, 183.460 KM and 188.882 KM respectively of Gauripur – Bilasipara Section of NMX – JPZ New B.G. Line Project of N. F. Railway.

01/11/2017

CE/CON/J-I/Tunnel No.12/2014/33

W/362/CON/Tunnel No.12/2014/33

20/07/2015

HCC-CPL (JV)

Construction of single line BG Tunnel No.12 (approx. length 9551.00 Rm) from ch.105840.00 to 115391.00 Adit-1 (approx length 1440.00m) at ch.112623.00 and Adit-2 (approx length- 420.00m) at ch.115391.00 in between Tupul –Imphal in connection with construction of new Railway line project Jiribam-Imphal of N.F.Railway.(Construction).

19/11/2018

CE/CON/BLK-NMX(NJP) Pakur Ballast/2014/41

W/362/CON/BLK-NMX(NJP) Pakur Ballast/2014/41

07/10/2015

M/s. R.N.Jha

Manufacturing,supplying and stacking of 50mm size Pakur/ Bakudih variety machine crushed ballast on cess between Raninagar Jalpaiguri (excluding) to New Maynaguri from km 27.00 to km 45.78 in connection with Ambari Falakata to New Maynaguri BG doubling works. (Two Packet System).

01/09/2018

Dy.CE/Con-2/AGTL-Sabroom/Field Assistanc/2014/12

W/362/CON-2/AGTL-Sabroom/Field Assistance/2014/12/

31/12/2014

Shri Biswajit Deb

Providing assistance to the field officials/supervisors/ Land Acquisition team for their routine field works in connection with Agartala - Sabroom New Line Project under Dy.CE/ CON/AGTL.

30/12/2017

           

First : Previous [  1 ] Next : Last  

       
 

Powered by WebX