Back to Home Page

   
 

Available Tenders

 
 Search Tenders

View Store Tenders

Corrigendum

 
  Unit Location  
Department  
  Opening Date       (DD/MM/YYYY)  
  Tender No.
 

 Please Click on the Tender No. to see more details. You must login to download the tenders.
New Users can
Register here.

 

 Tender No

  Description

 Issue Date  

Receipt of Offer up to

Opening Date

Corrigendum

CE/CON/N-K/CRG/2017/09/RT-1

Loading, Unloading and transportation of Rails, PSC BG sleeper, PSC Turn out sleepers, other PSC spl sleepers, other P.Way fittings and materials etc. with including all lead, lifts and stacking at various locations and in station yards from Km. 88.0 to 176.0, in connection with the doubling project of NBQ-GLPT-KYQ.

26/06/2018

10/07/2018

10/07/2018 3:30:00 PM

Nil

CE/CON/N-K/ATW/2018/13

Alumino thermit welding (with single shot crucible) of Rail joints by Pre-heat (SKV)welding and automatic tapping thimble technique including supply of all required welding materials and equipments such as Thermit portion, three piece pre-fabricated mould, compressed air petrol mixture preheating system etc. as per the requirement between Km 88.00 to Km 176.00, in connection with NBQ-GLPT-KYQ Doubling project of N.F. Railway.

26/06/2018

10/07/2018

10/07/2018 3:30:00 PM

Nil

CE/CON/N-B-D/SUR/2018/08

Final location survey using Digital Terrain / Elevation Model (DTM/DEM/DSM) generated from satellite or LiDAR imageries, staking of alignment on ground, Geological & Geophysical mapping & Geo-Technical investigations, planning & design of tunnels, bridges / viaducts & other structures, preparation of plans & detailed estimate etc. in connection with North Lakhimpur -Ziro(125kM) and Bame-Daparijo(60KM)BG single Railway line in Arunachal Pradesh .(approx. length- 185Km.)

22/06/2018

06/07/2018

06/07/2018 3:30:00 PM

Nil

CE/CON/D-K/EMB/2018/07

Earthwork in bank & cutting, construction of minor bridges, protection work and other related works for approach road to Portal-1 of Tunnel -3 and Br. No. 88 in connection with the Dimapur (Dhansiri) - Kohima (Zubza) New line project.

22/06/2018

06/07/2018

06/07/2018 3:30:00 PM

Nil

DyCE-C-I-Drain-HL-18-8

Construction of side drain between Railway Km 189/050 - 189/825 as per demand of local civil authority to drain out storm water which was blocked during construction of LMG-SCL Gauge Conversion work.

19/06/2018

03/07/2018

06/07/2018 10:00:00 AM

Nil

DYCSTE_C_APDJ_2018_11_05

Provision of OFC & 6 Quad cable involving trenching, laying and their termination along with supply, installation, testing and commissioning of SDH Add/Drop Mux (STM-1), Primary Mux along with other associated equipments in Gumanihat-New Maynaguri section of Alipurduar Division of NF Railway, in connection with the work of Gumanihat-New Maynaguri Doubling works.

28/05/2018

03/07/2018

03/07/2018 3:30:00 PM

Nil

CE/CON/H-N/MIS/2018/04

At Naharlagun(Arunachal Pradesh)- Construction of filter water overhead tank, air compressor room, pump house, double storied office building for pit line maintenance staff shed, extension of washing pit line and other ancillary work in connection with Harmuty-Naharlagun BG line project.

19/06/2018

03/07/2018

03/07/2018 3:30:00 PM

Nil

CE/CON/B-B/PW/2018/03

Quarrying and supplying of 66000cum (approx.) man size balasted boulder for long term repair/maintenance of existing South Guide Bund, weighing 40 Kg to 70Kg and stacking at Bogibeel Bridge site (inside dyke) on South Bank of River Brahmaputra in connection with construction of Bogibeel Bridge Project at Bogibeel near Dibrugarh.

19/06/2018

03/07/2018

03/07/2018 3:30:00 PM

Nil

CE/CON/D-K/MIS/2018/06

Construction of Side drain,Retaining wall, P. Way Godown and miscellaneous works, overhead tank, approach road , development of circulating area and ancillary buildings etc at Dhansiri, Dhansiripar & Sukhovi in connection with DMV-KOHIMA New Line Project.

15/06/2018

29/06/2018

29/06/2018 3:30:00 PM

Nil

CE/CON/B-S/MIS/2018/03

Development of new approach road from highway (NH-54) to proposed Kawnpui Railway Station including construction of Road culvert, Retaining wall, side drain and maintenance for 3 years from the date of completion of work for the movement of security officials, inspecting omfafitceiraialsl , & machineries and to provide access to passengers to newly proposed Kawnpui Railway Station in connection with construction on New BG Railway line from Bairabi to Sairang.

12/06/2018

26/06/2018

26/06/2018 3:30:00 PM

Nil

CE/CON/N-K/TL/2018/07

Dismantling of existing track, linking of new BG track at yards & mid-section, TRR by 10/20 rail panel, Linking of points & crossing, SEJ, L-Xing etc. on PSC sleepers including insertion of turnouts, carriage of P-way materials etc., and all other connected ancillary works as per requirement in between Km 146.00 to Km 176.00, in connection with NBQ - GLPT - KYQ Doubling project of N.F. Railway.

12/06/2018

26/06/2018

26/06/2018 3:30:00 PM

Nil

CE/CON/N-K/TL/2018/06

Dismantling of existing track, linking of new BG track at yards & mid-section, TRR by 10/20 rail panel, Linking of points & crossing, SEJ, L-Xing etc. on PSC sleepers including insertion of turnouts, carriage of P-way materials etc., and all other connected ancillary works as per requirement in between Km 88.00 to Km 146.00, in connection with NBQ - GLPT - KYQ Doubling project of N.F. Railway.

12/06/2018

26/06/2018

26/06/2018 3:30:00 PM

Nil

CE/CON/N-K/TL/2018/05

Dismantling of existing track at yard & mid-section, linking of new BG service track and then TRR by 10/20 rail panel; Linking of points & crossing, SEJ, L-Xing etc. on PSC sleeper including insertion of pre-assembled turnout, carriage of sleepers & rails, spreading of ballast etc. and all other connected ancillary works as per requirement in between Km 43.00 to Km 88.00 in connection with NBQ - GLPT - KYQ DL work of N.F. Railway

12/06/2018

26/06/2018

26/06/2018 3:30:00 PM

Nil

CE/CON/N-K/TL/2018/04

Dismantling of existing track at yard & mid-section, linking of new BG service track and then TRR by 10/20 rail panel, Linking of points & crossing, SEJ, L-Xing etc. on PSC sleepers including insertion of pre-assembled turnout, carriage of sleepers & rails, spreading of ballast etc., construction of 3 line washable apron at NBQ yard and all other connected ancillary works as per requirement in between Km 00.00 to Km 43.00, including NBQ yard, in connection with NBQ-GLPT-KYQ Doubling project of N.F. Railway.

12/06/2018

26/06/2018

26/06/2018 3:30:00 PM

Nil

CE/CON/F-M/MB/2018/01/RT-1

Balance work of transportation of bridge girder from Manmad workshop to bridge site including erection, field rivet, welding and other ancillary works in between Raninagar Jalpaiguri to New Maynaguri in connection with ABFC-NMX doubling works.

12/06/2018

26/06/2018

26/06/2018 3:30:00 PM

Nil

         

First : Previous [  1 ] Next : Last  

         
 

Powered by WebX